Method statement of Tiling work

Bạn đang xem bản rút gọn của tài liệu. Xem và tải ngay bản đầy đủ của tài liệu tại đây (697.76 KB, 19 trang )

CÔNG TY CỔ PHẦN XÂY LẮP THƯƠNG MẠI 2
Architects & Construction Service Corporation

METHODSTATEMENT
SMC Manufacturing (Vietnam) Factory-phase 1 Project

TILING WALL & FLOOR
FACTORY No.1

Ref No:

SMC-ACS-MS-01-TLW-001

ACSC- CONG TY CO PHAN XAY LAP THUONG MAI 2

SMC-Factory No.1/MS-Tiling work

Page 1


CÔNG TY CỔ PHẦN XÂY LẮP THƯƠNG MẠI 2
Architects & Construction Service Corporation

Revision History
Revision
01

Date of issue
29/February/2016

Purpose of issue (approved/ revision)


For Approval

Submitted by ACSC
Prepared by
Reviewed by
Approved by

Name
Lê Long Hậu
Nguyễn Hoàng Trinh
Nguyễn Văn Trung

Position
Deputy Site Manger
Site Manager
Project Manager

Date

Signature

Approved by KOA
Checked by
QA-QC
QA-QC
HSE
KDA

Position


Date

Signature

Reviewed by
Approved by

Approved by Client Name
Prepared by
Reviewed by

SMC-Factory No.1/MS-Tiling work

Position

Page 2

Date

Signature


CÔNG TY CỔ PHẦN XÂY LẮP THƯƠNG MẠI 2
Architects & Construction Service Corporation

Contents

SMC-Factory No.1/MS-Tiling work

Page 3



CÔNG TY CỔ PHẦN XÂY LẮP THƯƠNG MẠI 2
Architects & Construction Service Corporation

1. INTRODUCTION
1.1. PURPOSE
This method statement describes the methodology for tiling of wall and floor at SMC project
Tiling work will be carried out after all constructions of relevant structures such as slab, columns,
wall completed, but before painting and installing of sanitary wares. The concrete work, brick work
constructions were covered by another submittals, therefore they will no longer discussed in this
method statement.
Before tiling work can start, all electrical and plumbing works inside the wall, if any, have been also
completed, fully tested and approved. All door, window frames have been installed as well.
Tiling work will start only the working drawing has been prepared. Working drawing will be
separate submitted with this document.
Tiling work will be divided into two stages: firstly tiling the wall then tiling the floor.

1.2. DEFINITIONS:
PROJECT PARTICULARS:
Project name

: SMC MANUFACTURING (VIET NAM) FACTORY-PHASE 1 PROJECT

Address

: Long Duc Industrial Park, Long Duc Ward, Long Thanh District, Dong Nai Province,
Viet Nam.

PARTY:

Client/ Owner : SMC MANUFACTURING VIETNAM CO., LTD
Contractor

: KAJIMA OVERSEAS ASEA PTE LTD.
Responsible for the supervision of Contractors who will construct the podium and all
related activities as outlined in this procedure.

SCOPE OF WORK
The works to be carried out by Sub-Contractor (ACSC) and shall apply for works at Factory No.1of SMC
MANUFACTURING (VIET NAM) FACTORY-PHASE 1 PROJECT.
1. Construction Reinforcement Concrete Structure works included:
a. Pile head treatment
b. Earth work
c. Formwork
d. Reinforcement Steel Rebar work.
e. Concrete work

2. Finishing works included:
SMC-Factory No.1/MS-Tiling work

Page 4


CÔNG TY CỔ PHẦN XÂY LẮP THƯƠNG MẠI 2
Architects & Construction Service Corporation
a.
b.
c.
d.


Brick work.
Plaster work.
Painting work.
Tiling work (Wall & Floor).

2. BUILDING DESCRIPTION:
Location:
Factory No.1 are located at the corner of Road No.D5 &N2-5 in Long Duc Industrial park as below

Factory No. 1
Description:
-

Building purpose :Factory
Foundation
: Spun piles (D300, 350, 400 mm)
Structure
:RC structures + steel rafter; Slab on grade.
Dimensions:
o Factory
 140m long (14x10m); 60 (4x15m) - 69m wide
 Ground Floor (FL. 0.00m); 1st Floor (FL. +7.25m)
 Height : 11.40m
o Utilities area: 2 x (120m long, 4.5m wide).

SMC-Factory No.1/MS-Tiling work

Page 5



CÔNG TY CỔ PHẦN XÂY LẮP THƯƠNG MẠI 2
Architects & Construction Service Corporation

GROUND FLOOR PLAN

-

Floor load:
o Factory Ground Floor
o WC Ground Floor
o Stair case
o Storage/Utilities

-

Slab thickness:
o Factory Ground floor slab
: 300 mm thk.
o Storage/Utilities Ground Floor slab : 150 mm thk.
o 1st Floor slab
: 140 mm thk.

-

Area:
o

o

: 40 KN/m2.

: 2 KN/m2.
: 3 KN/m2
: 10 KN/m2

Ground floor
+ Factory area
+ Storage/Utilities area
1st Floor

SMC-Factory No.1/MS-Tiling work

: 9561 m2
: 8400 m2
: 1161 m2
: 9561 m2

Page 6


CÔNG TY CỔ PHẦN XÂY LẮP THƯƠNG MẠI 2
Architects & Construction Service Corporation

3. ORGANIZATION CHART
3.1. Organization Chart (Factory No.1)
Project Manager
NGUYỄN VĂN TRUNG (MP: 090 330 7742)


Site Manager
NGUYỄN HOÀNG TRINH (MP: 090 291 1235)



Deputy Site Manager

Deputy Site Manager

NGUYỄN TRÍ KHOA (MP: 093 722 9680)

LÊ LONG HẬU (MP: 093 232 5944)





Site Engineer

QC engineer

NGUYỄN MINH TUẤN (MP: 098 314 5069)

PHAN QUỐC TRƯỜNG (MP: 098 314 5069)

NGUYỄN VĂN HÀO (MP: 093 872 2730)



Safety Supervisor

Shop Drawing


ĐỖ VŨ QUYỀN ANH (MP: 090 853 1908)

NGUYỄN VĂN THIỆN (MP: 090 657 5516)


Construction Teams

3.2. Assignment
Position
Deputy Site manager
Site Engineer
QA&QC Engineer
Safety Supervision

SMC-Factory No.1/MS-Tiling work

Factory No.1
NGUYỄN TRÍ KHOA

Factory No.9
TRẦN AN TOÀN

NGUYỄN MINH TUẤN
NGUYỄN VĂN HÀO
PHAN QUỐC TRƯỜNG
ĐỖ VŨ QUYỀN ANH

LÊ VĂN TUẤT
PHẠM TRỌNG HÙNG
NGUYỄN ANH ĐỨC

PHẠM VĂN MẠNH

Page 7


CÔNG TY CỔ PHẦN XÂY LẮP THƯƠNG MẠI 2
Architects & Construction Service Corporation

4. SCHEDULE
Construction Schedule of tiling work on Ground Floor Toilets as below:
Work
Wall tiling
Floor tiling

Start
01/3/2016
07/3/2016

Duration
6 days
5 days

Finish
06/3/2016
11/3/2016

Construction Schedule of tiling work on 1st Floor Toilets as below:
Work
Wall tiling
Floor tiling


Start
01/3/2016
11/3/2016

Duration
6 days
5 days

Finish
06/3/2016
15/3/2016

5. SPECIFICSTANDARD
Tiling floor and wall should be carried out in accordance with the requirements of:
-

SMC MANUFACTURING (VIET NAM) FACTORY-PHASE 1 PROJECT Specification finishing works.
Current Vietnamese Construction Standards.

TCVN 7132-2002:

Ceramic floor and wall tiles- Definition, classification, characteristics and
marking

TCVN 6415-2005:

Ceramic floor and tile- Test method

TCVN 6414-1998:


Ceramic floor and tile- Specifications

TCVN 8264-2009:

Wall and floor tiles- Codes of practice and acceptance

TCVN 9377-2012:

Finish works in construction – Execution and acceptance. Part 1: paving and
smoothing works

TCVN 9377-2012:

Finish works in construction – Execution and acceptance. Part 3: wall tiling
works

TCVN 7899-1-2008

Ceramic tiles - Grouts and adhesives – Part 1: Terms, definitions and
specifications for adhesives.
Ceramic tiles – Grouts and adhesives – Part 2: Test methods for adhesives
Adhesives for Tiles – Specifications and Testing Methods

TCVN 7899-2-2008
TCXDVN 336- 2005

SMC-Factory No.1/MS-Tiling work

Page 8



CÔNG TY CỔ PHẦN XÂY LẮP THƯƠNG MẠI 2
Architects & Construction Service Corporation

6. SCOPE OF WORKS:
All tiling work of Factory No.1 designated for the Toilets (8 rooms) on Ground floor and 1 st floor. The
tiling in Office area will be carried out by other Sub-Contractors. This work includes screeding and tiling
of wall and floor.

The toilets where
tiling are applied

TYPICAL FLOOR TILING

TYPICAL WALL TILING
SMC-Factory No.1/MS-Tiling work

Page 9


CÔNG TY CỔ PHẦN XÂY LẮP THƯƠNG MẠI 2
Architects & Construction Service Corporation

7. FLOW CHART AND DIRECTION OF WORK
The work sequence of tiling floor and wall are shown at the following flowchart.

1. Columns, slab, wall construction

2. Installing door, window frame


3. Electrical work, plumbing, waterproofing

Start of Tiling

1. Set up tile layout

2. Wall tiling (plastering, applying)

3. Floor Tiling (screeding, applying)

4. Filling paste to the joints

5. Cleaning tiles

End

SMC-Factory No.1/MS-Tiling work

Page 10

Covered by previous submittal


CÔNG TY CỔ PHẦN XÂY LẮP THƯƠNG MẠI 2
Architects & Construction Service Corporation

8. PREPARATION WORKS
8.1. Cleaning and check
Sub-base surface:

- Remove any dust, dirt, foreign matter on the wall, floor.
- Damp the wall, floor surface with clean water.
Tiles:
- Check dimensions, shape of tile to ensure their uniformities.
- Moisten all tiles by soaking in the water for a while.

8.2. Mock up
The mock-ups for tiling work on site will be done by ACSC before application for all toilets. The location
of mock-up with the plan layout drawings shall be proposed and submitted by ACSC to Kajima Vietnam
for approval. The location of mock-ups shall be chosen by KOA in such a way that the openings of a door
and window, floor drains, penetrated pipes, floor and wall shall be involved.

8.3. Forming the bed of tiling
Wall tiling:
- Check the distance of the walls to suit with the tile layout
- Using theodolite to set up all finished planes of wall tile to ensure their plumbness, flatness and
perpendicularity at the corners. Mark the set up lines onto the walls.
- Using string to set base points for the plaster coat onto the walls by deduct the thickness of the tile.
- Apply the method of plaster work to plaster onto the wall to get true surfaces where the tiles will be
applied. Tile backing shall be cement plaster applied in conformity with requirements in the specification.
Floor tiling:
- Based on level benchmark and designed slope of the floor, set up the finish surface of floor tiles then
mark its intersection lines with the walls onto the wall surfaces.
- Using string to set base points for the screed layer onto the floor slab by deduct the thickness of the
tile.
- Level pegs shall be installed by following marked lines on floor surface for water dividing lines to keep
the floor slope at least one day before floor screed. The spacing of level pegs shall be less than 2.0 m.
- For toilet floor areas which are waterproofed, a special care of protection to waterproof layers shall be
taken by Subcontractor. Material for installation of level pegs shall be screed mortar.
- Screed the mortar onto the slab then flatten with tool such as straight bar. Mortar to bed is of 1

cement to 3 sand mixture and well mixed on the site.
- A straightedge tolerance of 2.0mm/2m shall be allowed for floor screed surface finish.
- Trowel by hand to get a true, flat finish surface.

SMC-Factory No.1/MS-Tiling work

Page 11


CÔNG TY CỔ PHẦN XÂY LẮP THƯƠNG MẠI 2
Architects & Construction Service Corporation

8.4. Set up tiles layout
- All check lines for walls of room and grid lines shall be re-marked on floor screed. Marked lines such
as check lines and grid lines on floor shall be matched to lines marked on walls.
- Room dimensions, wall corners, wall lines shall be checked for right angle based upon on the marked
lines. If any discrepancies are found then repair shall be carried out and accepted by Kajima Vietnam
before tiling or other finish.
- For wall tiling, the Subcontractor shall ensure that the lines of FFL+1000 (Floor Finish Level)
and the lines for the top layer and first layer of wall tiles to be marked sufficiently and correctly
- Based on the working drawing, using the level machine, theodolite, measure tape to set up the tiles
layout and mark the tile joints onto the wall or floor bed. The dimensions of tiling area will include the
width of the tiles and the joints which shall be uniform 2mm wide.
- Tiles will be arranged so that there will be no tile has the width smaller than the half width of their
original dimensions. They will also be set so that the center of any fitting such as floor drain, faucet will be
right on the intersection of the joints.

9. CONSTRUCTION METHOD
9.1. Mortar & mixing mortar
- Sand for mixed mortar shall be natural sand free from any deleterious materials such as clay, flaky

or elongated particles, mica, shale or other laminated materials, organic impurities, iron pyrites. Sand shall
be clean, hard, durable, crushed. It shall be thoroughly washed and all dirt, shells etc…removed before use.
- Water for brick work shall be clean and uncontaminated potable water from the city main supply or
any other approved source free from harmful matter.
- Mortar type to be used shall be sand-cement mortar, class mark #100 (28days compressive strength
7.5 Mpa) with its proportion: 1 part of cement: 4 part of sand in volume
- The mortar proportion will be verified with the result of trial mix on site and testing prior to be use.
- Mortar will be mixed by mixer which has capacity of 100 liters on site. Material of mortar will be
measured in containers with defined volume to maintain control and accuracy of proportion.
- Mix by placing one-half the water and sand in operating mixer. Then add cement and remainder of
sand and water. Mix batch for not less than 3 minutes after all ingredients are in the mixer.
- Workability or consistency of mortar on the board shall be sufficiently wet to be worked under the
trowel.

9.2. Tiling sequence:
- Ceramic tiles shall be or soaked in water before installation.
- Tile will be installed by using thin set of tile grout to apply on the prepared bed surface. The
thickness of cement adhesive will not exceed 3mm.
- To ensure a uniform of joint width, PVC spacers shall be used to ensure joint width shall be 2.0 mm.
Wall tiling:
- Wall tiling will start row by row from the bottom to the top.
SMC-Factory No.1/MS-Tiling work

Page 12


8x250+2x7=2014

CÔNG TY CỔ PHẦN XÂY LẮP THƯƠNG MẠI 2
Architects & Construction Service Corporation


DIRECTION OF TILING

2mm

- PVC beads shall be installed at outer corners of wall and PVC tiling bead joint shall be butt or mitred at
ends.

SMC-Factory No.1/MS-Tiling work

Page 13


CÔNG TY CỔ PHẦN XÂY LẮP THƯƠNG MẠI 2
Architects & Construction Service Corporation

30
10 20
2

2

10 20

WALL TILE FINISH

Tile size

2


2

30

Tile size

WALL

PVC ANGLE BEAD

- At the inner corners, there will be joints 2mm wide. The termination of wall tiling at inner corner
of wall shall follow the principal of “Joint line of wall tiles at inner corners shall be invisible for
the direction of view from room entrance”.

WALL TILE
2mm JOINT
GRANITE STONE

80

20
180

80

20

2mm JOINT

30


WALL TILE

10 20
30

80

-Where tiles connect with door frame, there will be joint 5mm wide then filling with sealant.

SMC-Factory No.1/MS-Tiling work

Page 14


CÔNG TY CỔ PHẦN XÂY LẮP THƯƠNG MẠI 2
Architects & Construction Service Corporation

SEALANT

5

80

10

15 10

CERAMIC TILE


15

DOOR FRAME
200
RC STILLENER

40
20

- Permanently using straight bar to check the plumpness, flatness of the finished surface; square
meter to check the perpendicularity at the intersection of the walls.
- Always cleaning the tile surface to ease the inspection of tiling.
Floor tiling:
- Floor tiling should be carried out after the wall tiling completed. Unless specified on the drawings,
floor tiling joint lines and wall tiling joint lines shall be aligned and the wall tile installation must be
completed before floor tiling.
- The floor tile arrangement for 2 rows in perpendicular directions from start point on the floor shall
be carried out to check the correctness between the drawings and the actual site condition
- Where the floor is required to slope the Subcontractor shall check for floor tile joint line at water
dividing line. The level of installed tiles along the water dividing line shall be at the required level to
ensure the design slope.
- Floor tiling shall start from the centre of the room. In order to avoid any cumulative error of floor
tile installation, the start of floor tiling from the room corner shall be avoided.

SMC-Factory No.1/MS-Tiling work

Page 15


CÔNG TY CỔ PHẦN XÂY LẮP THƯƠNG MẠI 2

Architects & Construction Service Corporation

- Permanently using straight bar to check the flatness of the finished surface; spirit level to check the
slopping of the floor.
- Always cleaning the tile surface to ease the inspection of tiling.
Work sequence:
- Preparing the right tile units. Cutting, beveling them before, if necessary.
- Fully plastering the adhesive onto the back of the tiles.
- Placing the tile unit in position.
- Slightly move and press the tile to the bed surface.
- Using rubber hammer to slightly clap onto the tile.
- Insert the plastic stick the check the joint width and adjust the tile until get the true position.
- Using straight bar the check the flatness of the tile unit with the true surface.
- Repeat the clapping, adjusting the tile unit until it reach all requirements.

9.3 Finishing:
Filling the joints:
- Using white cement grout to paste onto the wall, floor tiles to fill the joints.
- Before grout become set, using clothes or sponge to skillfully remove the excess grout to make the
joint neat and clean.
- The surfaces of joints have to be flush with the tile surface.
SMC-Factory No.1/MS-Tiling work

Page 16


CÔNG TY CỔ PHẦN XÂY LẮP THƯƠNG MẠI 2
Architects & Construction Service Corporation
Cleaning, protecting:
- Thoroughly remove any stains of grout, dust on the tile surface.

- Protect the tile from damages of any following construction activities. Special cares should be taken
with hard and heavy tools, equipment such as door, scaffolding, machine…

10. RESOURCES
10.1. TOOL & EQUIPMENT
The equipment to be used for the construction of s is listed below.
No.
1

Specification
100 liters

Description
Concrete mixer

Unit
ea

Q’ty
2

2

Cutting machine

ea

2

3


Tools (measure tape, rubber hammer,
spirit level… etc)

ea

1

4

Theodolite, level machine

ea

1

5

Scaffolding

set

1

Remarks

10.2. MATERIALS
Type of material:
No.


Item
Type

1

Floor & Wall tiles

2

Tiling bead

3

Cement

4

Description
Size

Origin

Ceramic

300x300 (mm)

Royal 302137

PVC


10x10x15 (mm)

T10-W

Package

PC40

Fico, Nghi son

Tile Grout (adhesive)

Ready mixed

25kg/bag

Striving method

5

Joint filler (White)

Ready mixed

1kg/bag

Skymax

4


Sand

Fine

Dong Nai

As approved material

6

Water

Kajima

Materials handling, storage and delivery
- Tile:
Tile will be sealed at firm and delivery to site by truck
It should be keep in warehouse and level ground with the height not exceed 1.5m.
- Cement:

SMC-Factory No.1/MS-Tiling work

Page 17


CÔNG TY CỔ PHẦN XÂY LẮP THƯƠNG MẠI 2
Architects & Construction Service Corporation
Cement bags delivered should be stored at enclosed storage with 100mm above ground level and
covered by plastic protection in order to prevent the moisture. The cement bags shall be stored in piles
not more than 8 bags high.

- Sand:
Sand will be stock on site on the plastic sheet. Before using, it will be screened to remove the rubbish
and other impurities.
Other materials are keeping in storage and they are transported to the site work when they are in
used.

11. QUALITY CONTROL

-

-

All tile should be procured from approved sources.
Tile will be delivered to site under control of the Procurement Section and attach certificate of
origin clearly.
- All material (cement, sand) need to take sample and approve before order
delivery.
The tolerance of tiling work will follow KOA ITP shown in Appendix 4.
Refer some tolerances for inspection in Contract Technical Specification.
Tolerance for flatness:
Hollowness for installed floor tiles :
Hollowness for installed wall tiles:
Tolerance for verticality of installed
wall tiles:

Straightedge 2.0 mm/ 2.0 m.
Not allowed
Maximum 10% at corners of installed tiles allowed
but not exceed 10% of the wall area.
+/- 2.0 mm / 1.0 m high but not exceed

5.0 mm
for the whole wall height.

Tolerance for level:

+/- 2.0 mm.

Tolerance for alignment of tiling joint
lines :
Deviation between adjacent tiles :
Tolerance for joint width:

2.0 mm/ 3.0 m long but not cumulative.

Tolerance for joint width:

+/- 2.0 mm if joint width greater than 6.0 mm

Not exceed 0.5 mm.
+/-1.0 mm if joint width less than 6.0 mm

12. APPENDIX
Appendix-1: Inspection test plan
Appendix 2: Checklist
SMC-Factory No.1/MS-Tiling work

Page 18


CÔNG TY CỔ PHẦN XÂY LẮP THƯƠNG MẠI 2

Architects & Construction Service Corporation

END