Task 1
Explain the purpose of the following project document.
A)
Gantt chart:
A Gantt chart gives information about the activities that make up a
project on a horizontal bar chart. The project activities are list in
sequential order with the horizontal bars representing the time
required to complete each activity. The chart is a graphic
representation of the relationship between project activities and time.
When your Gantt chart is complete, It can be seen:
•
The minimum total time required for each activity and the entire
project
•
The correct sequence of activities
•
Activities that can be done at the same time
•
Slack time (shown with dotted lines) that occurs when no
activities are being performed
B) Action plan:
Is a formal document that guides the execution and control the
project and outlines how the project objectives will be achieved by
listing the major tasks, resource required and time frames required for
each project activity. Action plan is established at the beginning of
project to plan for progress, work, cost, method of management. It
makes the achievement of the project’s objectives and ensures all
aspects and activities required to implement the project are covered.