Promoting Quality Awareness for
Subcontractor Managers

We Must Be
On Target For

QUALITY

Prepared & Presented by Ken Toth (JVD Deputy QCM) & David I. Cockle (JVD Chief QCE) on 26 Sept. 2015

NSRP Project

1


Introduction
 There has been a recent increase in major non-conformances
issued for serious violations over the past several months.
 This workshop focuses on encouraging Subcontractor
Management to become more involved, and promote quality
improvements.
 We are here to convince you that quality is an asset, not a
obstacle to schedule or profit, as is often mistakenly thought.
Our challenge is to maintain a high standard of quality in
Vietnam.

If you succeed, we succeed!
NSRP Project

2



Civil Subcontractors

NSRP Project

3


Commitment to Quality
If I can convince you throughout this workshop
that by making quality a much higher priority
and improving it, you will:
1. Save money
2. Automatically improve safety
3. Meet your current schedule
would you agree to commit to raising the
standards of quality and make improvements?

Yes!!!
NSRP Project

4


Construction’s Biggest Problems!!!
There are three (3) main issues that cause the biggest
problems to the Senior Management of any construction
project:

Schedule – Cost – Safety

QUALITY is the silent partner of all, but it can have a
significant positive impact on the other three.
Without quality, schedule, cost and safety always suffer.

NSRP Project

5


JGCS & Client Concern
 JGCS and the Client
have become very
concerned with the
quality of the work.
 Subcontractors are
now under the
spotlight.

Quality

“Quality is Under the
Magnifying Glass”

NSRP Project

6


Quality Concerns
In the pursuit of progress, quality often takes a backseat to

safety and schedule. We often forget that non-conformances
for substandard quality work are the largest contributor to
the project cost overruns and missed schedules.
Let us look at a few photographs of the civil quality concerns
which have been raised over the past few months.
These are namely:
 Civil Excavation and Dewatering Work.
 Material Storage for Rebar & Structural Steel.
 Backfill and Compaction and the use of unsuitable and
contaminated soil.
 Structure Settlement
 Concrete Curing & Defects.
NSRP Project

7


Quality Concerns

NSRP Project

Tell me and
I’ll Forget……
Show me and
I’ll Remember!

8


Quality Concerns

Backfill, Compaction
& Contaminated Fill

NSRP Project

9


Quality Concerns

Backfill, Compaction &
Contaminated Fill
NSRP Project

10


Quality Concerns

Backfill, Compaction
& Contaminated Fill
NSRP Project

11


Quality Concerns
Civil Excavation
& Dewatering


NSRP Project

12


Quality Concerns
Erosion & Undermining

NSRP Project

13


Quality Concerns

Poor Construction Methodology
NSRP Project

14


Quality Concerns

Poor Construction Methodology
NSRP Project

15


Quality Concerns

Soil Settlement

NSRP Project

16


Quality Concerns
Soil Settlement

NSRP Project

17


Quality Concerns

Soil Settlement under
Equipment Foundations
NSRP Project

18


Quality Concerns

Soil Settlement under
Equipment Foundations
NSRP Project


19


Quality Concerns

Poor Storage results in material loss,
damage and wastage of manpower
resources required for cleaning.

NSRP Project

20


Quality Concerns

Poor Storage results in material
loss, damage and wastage of
manpower resources required
for cleaning.

NSRP Project

21


Quality Concerns

Poor Storage results in material loss, damage and
wastage of manpower resources required for cleaning.

NSRP Project

22


Quality Concerns

Poor Material Storage
NSRP Project

23


Quality Concerns

NSRP Project

24


Quality Concerns

Poor Material Storage
NSRP Project

25


×